Construction Project of Busa wangdue gonpa buddhist college


Construction of Hostels/Dormitories & Kenpo quarter

98% Completed 

All structural, masonry, rod binding, timberworks, internal and external painting and plastering works, electrical and plumbing wiring and fitting works.

Balance  works(2 %)

Timber flooring, window shutter, door shutter will be completed with tshongkhang and other  buildings as timber infestation can occur or will be rotten/ effected  with fungal decay until completeion of tshongkhang building

Administration blocks, Guest house , Dinning hall & Kitchen

95% Completed

All structural, masonry, rod binding, timberworks, internal and external painting and plastering works, Electrical & plumbing wiring works

Balance Works (5%)

Minor finishing works are to be executed and complete along with tshokhang.

Congregation Hall (Tshokhang)

70% Completed

All structural/roofing works completed. GRC works-all measured and tender works executed and will be awarded to Bhutan GRC company. Main rabsey-70% completed. Windows-100 percent completed. Internal AAC block partition-70%completed. Internal plaster-70% completed. Exterior crm works-80 %completed.