Construction Project of Busa wangdue gonpa buddhist college
Construction of Hostels/Dormitories & Kenpo quarter
98% Completed
All structural, masonry, rod binding, timberworks, internal and external painting and plastering works, electrical and plumbing wiring and fitting works.


Balance works(2 %)
Timber flooring, window shutter, door shutter will be completed with tshongkhang and other buildings as timber infestation can occur or will be rotten/ effected with fungal decay until completeion of tshongkhang building
Administration blocks, Guest house , Dinning hall & Kitchen
95% Completed
All structural, masonry, rod binding, timberworks, internal and external painting and plastering works, Electrical & plumbing wiring works

Balance Works (5%)
Minor finishing works are to be executed and complete along with tshokhang.

Congregation Hall (Tshokhang)


70% Completed
All structural/roofing works completed. GRC works-all measured and tender works executed and will be awarded to Bhutan GRC company. Main rabsey-70% completed. Windows-100 percent completed. Internal AAC block partition-70%completed. Internal plaster-70% completed. Exterior crm works-80 %completed.